Knowledge Hub

The calendar month trap: when severe weather falls between two months

20 November 2026

Dr Stuart Kings

NEC4 Drafter & Co-author

PhD, MRICS, MCIPS, BSc (Hons)

Construction workers at building site on a cloudy day
5 minutes read

NEC4 measures weather one calendar month at a time. A four week cold snap that straddles two months can fail the test completely, and contractors need to plan for it.

 

A blinkered view by design

Clause 60.1(13) does not ask whether the weather over a period was exceptional. It asks whether a weather measurement recorded within a calendar month was worse than the 1 in 10 year value for that month. The calendar is the unit of measurement, not the event.

Dr Stuart Kings, one of the nine drafters of NEC4, called this point “quite profound” at Sypro’s Knowledge Hub webinar on 10 November, and described the result as looking at the weather “in a blinkered fashion per calendar month”.

 

How the trap works

Stuart gave an example. A contractor encounters heavy snow over the last two weeks of November and the first two weeks of December. Measured across those four weeks, the contractor has clearly suffered weather worse than could be expected.

But the clause does not measure four weeks. It measures November, then December. Two weeks of snow may fall short of the November threshold. The other two weeks may fall short of, or only marginally exceed, the December threshold. As Stuart put it, “it’s a dead duck, and it’s not a compensation event.”

He added, with some humour, that a contractor with “a hotline to the weather gods” would ideally make all the bad weather fall in one calendar month. Without that hotline, “if the bad weather spans two kind of months, then unfortunately, it’s tough.”

 

The same logic applies to rainfall

The trap is not limited to snow. Two of the four standard weather measurements concern rain: cumulative rainfall per calendar month, and the number of days with rainfall over 5mm. A wet spell from the middle of one month to the middle of the next splits both totals. Each month may look ordinary on paper, even though the site has been waterlogged for weeks.

CECA’s bulletin on assessing weather delays confirms the approach: weather is recorded within a calendar month at the place stated in the Contract Data, and only the difference between the recorded value and the 1 in 10 year value is considered.

 

What contractors can do

Price for it. Treat weather straddling two months as a risk that will usually fall on you. The Met Office planning averages give the expected conditions for each month and help set realistic weather allowances.

Watch both months. When severe weather starts late in a month, request the Met Office report for that month and the next. It is possible for one month to qualify even when the other does not, and only the qualifying month can be a compensation event.

Record daily effects. Even where a month passes the threshold, only the extra over days count, and only if they affected the work. Daily site diaries showing which activities were stopped, and why, are essential.

Raise it at tender. Where the works are particularly exposed, ask whether additional weather measurements or an additional compensation event could share the risk more fairly. Once the contract is signed, the opportunity has gone.

 

Evidence wins borderline months

Where a month is close to the threshold, the quality of the evidence decides the outcome. CECA’s bulletin points out that proving the weather event is usually straightforward, because the data is published, but proving its impact is harder. Snow that turns to slush or ice, or covers only part of the Site, raises questions that only contemporaneous records can answer.

The Contract Data names the place where weather is recorded. If that station is some distance from the Site, local conditions may differ from the official record. The contract follows the named location regardless, so contractors should understand at tender which station applies and how representative it is of their Site. Clients choosing the location should pick the most representative station that records the measurements they need.

 

What clients can do

Clients cannot change the calendar, but they can change the risk. The more weather risk a contractor is asked to carry, the more it will price into the tender and into every compensation event. Stuart’s advice was to be fair and pragmatic at tender. A client who understands the calendar month trap can decide deliberately whether to accept that cost or share the risk.

 

Notify anyway, and early

None of this is a reason to stay quiet. Where weather looks likely to qualify, notify the compensation event within the eight week period in clause 61.3 and support it with data. Early warnings matter too: a contractor that could have warned of a weather risk and did not may see the compensation event assessed as if it had.

Managing these notifications and the supporting reports through one system, with every timescale tracked, means that when a month does qualify, the contractor is ready to prove it.

 

Sources

CECA, NEC Bulletin No. 48: Assessing weather delays under NEC contracts (December 2024). https://ceca.co.uk/wp-content/uploads/2024/12/CECA-NEC-Bulletin-Nr-48-Assessing-weather-delays-under-NEC-contracts-December-2024.pdf

Met Office, Construction catalogue guide: Planning Averages and Downtime Summary Reports. https://www.metoffice.gov.uk/binaries/content/assets/metofficegovuk/pdf/business/sectors/construction-catalogue-guide-v2.pdf

Pinsent Masons, Navigating weather conditions in Hong Kong SAR NEC4 contracts (March 2025), which also summarises the standard NEC4 ECC weather test. https://www.pinsentmasons.com/out-law/analysis/nec-risk-allocation-for-weather-events

Speaker quotes: Dr Stuart Kings, Sypro Knowledge Hub webinar, 10 November 2026.